Construction - Managing Practical Completion and the Defects Liability Period

8 steps. PC to final retention. Nothing missed.

Step by step
1
Pre-PC WalkthroughJobs

Walk the project with the client or CA 1-2 weeks before PC target. Classify outstanding items as PC-blocking or post-PC snagging. Document and share in writing.

2
Resolve Blocking Items and Submit PC NotificationeForms App

Clear all PC-blocking items and notify the client in writing. Submit practical completion notification per contract requirements (JCT or NEC).

3
Issue First Retention Release InvoiceInvoices

On receipt of signed PC certificate, raise the 50% retention release invoice the same day. Reference the PC certificate date on the invoice.

4
Log DLP Dates and Remaining RetentionProject Tracking

Record DLP start date, DLP end date, and remaining retention balance in the job record. Set a 4-6 week advance reminder before DLP end.

5
Manage Defect Notifications During DLPMentions

Log each client defect notification with date received and contract response deadline. Acknowledge in writing and confirm rectification date before attending site.

6
Obtain Written Clearance on Rectified DefectseForms App

After each rectification visit, get written sign-off from the client or CA confirming the defect is cleared. Do not assume closure without a written record.

7
Arrange Final Inspection and Obtain DLP CertificateJobs

At DLP end, arrange the final inspection walkthrough. Confirm all defects are cleared and obtain the Certificate of Making Good Defects or equivalent.

8
Issue Final Retention Release InvoiceInvoices

Raise the final retention release invoice on the same day the final certificate is received. Sync to accounting and close the job record once payment is confirmed.

What this workflow solves

DLP end dates aren't recorded at practical completion, so the final retention release invoice gets missed or issued months late.

Defect notifications from clients are handled verbally with no written log, making it impossible to prove what was reported and when.

The PC certificate is treated as the end of the job, so retention release invoices are never raised and thousands of dollars sit uncollected for months.

Frequently asked questions

See it live

Want to see this workflow in Zigaflow?

Book 30 minutes with Tim and we'll run through your exact process live.

Book a free demo →Build your own workflow
Workflow Builder

Got a different workflow?

Describe your process in plain English and we'll map it to Zigaflow in seconds.

Build my workflow →