Operations

Construction - measured term contract management

One contract. Many orders. One clear record.

Zigaflow Editorial

Published

Zigaflow Editorial publishes Zigaflow's guides, insights, industry resources, glossary and workflow pages. Zigaflow is responsible for what they say. Spotted an error? Email support@zigaflow.com.

Step by step

  1. Receive Work OrderJobs

    Log the work order from the contract administrator, recording scope description, property reference, and required completion date.

  2. Measure and PriceQuotes

    Visit the site to measure the scope and price the work against the agreed schedule of rates. Confirm labour, material, and sub-contractor requirements.

  3. Mobilize and ScheduleJobs

    Raise the job internally, assign operatives, and confirm material orders or sub-contractor bookings to meet the completion date.

  4. Complete Works and Record CostsPurchase Orders

    Complete the works, recording actual labour hours, materials used, and any additional items instructed on site that may qualify as variations.

  5. Compile Payment ApplicationInvoices

    Present measured quantities at agreed schedule-of-rates prices, plus any agreed additional items, with supporting site records.

  6. Submit and Track Certified SumInvoices

    Submit the payment application to the contract administrator. Record the certified sum and note any disputed items for follow-up in writing.

  7. Periodic Billing and ReconciliationInvoices

    Consolidate all completed orders into the periodic payment application, reconcile outstanding disputes, and issue the invoice once the certified sum is confirmed.

What this workflow solves

  • Work orders arrive continuously and without a central log it becomes impossible to track which are in progress, complete, or awaiting valuation - leading to missed items in the monthly payment application.
  • Pricing against a schedule of rates requires accurate on-site measurement records for each order; without them, disputed certified amounts are difficult to challenge at application stage.
  • Additional works instructed verbally during site visits are rarely given a separate reference, meaning they drop out of the payment application and are never billed.

Frequently asked questions

See it live

Want to see this workflow in Zigaflow?

Book a demo and we'll run through your exact process live.

Book a free demoBuild your own workflow

Got a different workflow?

Describe your process in plain English and we'll map it to Zigaflow.