Construction - managing a pay-less notice
Deadline-critical. Calculation-backed. Legally sound.
Step by step
- Application ReceiptJobs
Receive and log the subcontractor payment application, recording the date received, sum applied for, and the subcontract reference.
- Date MappingJobs
Identify the due date, final date for payment, and pay-less notice deadline from the subcontract. Calendar the deadline immediately.
- Commercial ValuationPurchase Orders
Assess the value of work properly executed and quantify all deductions - retention, contra-charges, set-off, and liquidated damages - with supporting documentation for each.
- Notice Drafting and ServiceInvoices
Draft the pay-less notice stating the sum considered due and the basis of calculation. Serve by the contractual method before the prescribed period deadline and retain proof of service.
- Payment ReleaseInvoices
Release payment of the sum stated in the notice by the final date for payment. Record payment and update job cost records.
- DocumentationJobs
File the issued notice, proof of service, valuation workings, and deduction evidence in the job record as an audit trail for any adjudication.
What this workflow solves
- Pay-less notice deadline dates are buried in subcontract documents and not tracked centrally, so commercial teams miss them under workload pressure and lose the right to deduct.
- Assembling a defensible valuation with itemised deductions takes time, and when job cost data is spread across emails, spreadsheets, and accounting records, the calculations arrive too late to meet the notice deadline.
- Issued pay-less notices are not filed systematically, leaving the business unable to produce an evidence trail quickly when a dispute goes to adjudication.