How to build a luminaire schedule for a lighting quote
In short
A luminaire schedule lists each fitting type with its reference, quantity, location and specification, and the quote and purchase order are both built from it. Number every revision of the schedule so all three documents match the current drawing.
- A luminaire schedule has one row per fitting type, not one row per fitting.
- Every row needs a stable reference, full product code, location, quantity and specification.
- Quote lines and purchase order lines should be taken directly from the schedule rows.
- Number each schedule revision and keep superseded versions so changes can be traced.
- Compare quantity totals per reference across schedule, quote and order before each issue.
A luminaire schedule lists every fitting type with its reference, quantity, location and specification. Learn how to build one, price a lighting quote from it, and keep quote and purchase orders aligned with each drawing revision.
A luminaire schedule is the table that defines every lighting fitting on a project, and it is the document a lighting quote is priced from. Each row describes one fitting type with its reference, quantity, location and specification. The quote takes its lines from those rows, and the purchase order to the supplier repeats them, so all three documents describe the same product. This guide shows how to build the schedule, what each row needs, and how to keep it under revision so the quote and the order always match the drawing.
Why the schedule comes before the price
On the plan, a fitting is only a symbol and a tag. The schedule tells you what the tag means. One source on fixture takeoff makes the point that type marks are project-specific, so a tag such as A1 can mean a recessed panel on one job and a decorative pendant on the next. Pricing from memory or from a count alone is how a quote ends up with the wrong product against the right quantity.
A luminaire is the complete lighting unit, so the schedule has to describe the whole unit, not just the lamp or the LED board. For businesses working in lighting and electrical, the schedule is also the point where design intent, the customer's price and the supplier's order meet.
What each row needs
Each row is one fitting type, not one fitting. Published guidance on fixture schedules lists similar columns: a type mark, a description, manufacturer and catalog number, mounting, voltage, wattage, lumens, color temperature, finish, optics, dimming or control method, emergency requirements and notes. For a quote, add three columns that the drawing set may not give you: location, quantity and unit price.
Keep the full product code
A shortened description hides options such as finish, optics and driver. Capture the complete catalog number where it is given, and flag it if it is incomplete rather than filling the gap yourself.
Collect the current drawing set
Gather the latest issued lighting plans, reflected ceiling plans, specification and any addenda. Note the revision letter or date of each sheet. Check whether the set contains a base schedule, separate alternates or schedules by area, because one row may not apply everywhere.
Assign a stable reference to every fitting type
Give each type a short, unique reference and never reuse it for a different product. If the designer has already issued marks, adopt them exactly. If you are building the schedule yourself, keep emergency fittings, controls and accessories on their own references so they are not lost in a total.
Record the specification for each row
Enter the description, manufacturer, full catalog number, mounting type, voltage, wattage, lumens, color temperature, finish, optics, driver and dimming method. Add the notes column last, since notes often change the price, for example a wet location rating or an emergency battery.
Count quantities by sheet and by location
Count each type on each plan sheet and keep the sheet reference with the count. Record the room or area as well. Separate counts make revisions easy to audit and stop fittings being missed or double counted where a floor continues across sheets.
Separate alternates, existing fittings and spares
Mark which rows belong to the base scope, which are alternates, and which fittings are existing and to remain. Add any spares or attic stock the customer has asked for as their own quantity, so they are visible on the quote.
Price each row and build the quote
Add the supplier cost, any accessories, and installation or commissioning where you are supplying and fitting. Each priced row becomes a quote line. Whether you build the quote in software or a spreadsheet, keep the reference column on every line so the price stays tied to its schedule row.
Issue the schedule with the quote and a revision number
Send the schedule alongside the quote and state which drawing revision it was built from. Number the schedule itself, for example Rev A, so the customer can see exactly what was priced.
Raise purchase orders from the approved schedule
Once the customer accepts, raise orders from the schedule rows, not from the quote summary. Each order line repeats the reference, full catalog number, finish and quantity. Purchase orders built this way give the supplier the same description the customer approved.
Revise the schedule when the drawing changes
When a new drawing revision arrives, update the schedule, raise the revision letter, and compare the changed rows against the quote and any open orders. Keep the superseded version rather than overwriting it, so a dispute over what was agreed can be settled from the record.
Common mistakes
The most common error is counting symbols without reading the schedule row behind them. Others are assuming that references mean the same thing from job to job, ignoring the notes column, missing separate emergency fittings, and pricing from an outdated drawing set. Controls are a further trap: a fitting that needs 0-10 V or DALI dimming can bring wiring and control scope that a fitting count alone does not show.
Check the revision before you send
A quote built on a superseded drawing can be correct line by line and still wrong for the project. Confirm the drawing revision at the moment the quote is issued and again when the order is placed.
Keeping the quote and order in line with the drawing
The discipline that matters is a single controlled schedule. The quote, the customer's approval and the supplier order should each point back to the same rows at the same revision. When a change comes in, change the schedule first, then the quote, then the open order. If you reverse that order, the three documents drift apart, and the difference usually surfaces on site when a fitting arrives in the wrong finish.
A simple check before each issue is to total the quantity per reference on the schedule, on the quote and on the order. If the three totals match for every reference, the documents agree. If one does not, find the revision that caused it before anything else goes out.