Deliver work

Labor columns on jobs/orders

In ZigaflowEssentials, Go and Momentum plans

The short answer

Labor columns on jobs and orders show forecast costs, actual costs and the labor price. Forecast costs are hours times the labor cost rate. Actual costs are actual hours times that rate. Price is forecast labor hours times the Labor Charge Rate. To charge by hours worked, enter actual hours as forecast hours.

The approach Zigaflow takes is that if you sell your products or services with a labor element, you have given a fixed price, instead of an estimate where the final price is based on the actual hours worked. This means that if you over-run or under-run the forecast hours, you will not pass that saving or cost to the customer. There is a work-around to this.

Explaining the Calculations

Forecast Costs

These are calculated by multiplying the hours by the labor cost rate, with the result shown in the 'Labour Total' column.

Item row in the Forecast Costings table with Hours/Unit 2.00, Labour Cost Rate 30.00 and Labour Total 60.00 highlighted

Actual Costs

These are calculated by multiplying the actual hours by the labor cost rate (to the left), with the result shown in the 'Actual Costs' - 'Labor Total' column.

Forecast and Actual Costings table with Labour Cost Rate 30.00, actual Hours 3.00 and actual Labour Total 90.00 highlighted

Pricing

Job costing table with red boxes on Forecast Labour Total, Actual Margin % and Item Pricing Labour Charge Rate values

This is calculated by multiplying the Forecast Labor Hours by the 'Labor Charge Rate', deriving the 'Labor Total' that is used in the price.

Based on Hours Worked

If your jobs/orders are based on the hours done, put these actual hours into the forecast hours. You can change the naming of this column in Settings -> Rename Line Item Fields.

Learn more: jobs in Zigaflow

Frequently asked questions

Next step

Tracking costs and profit on jobs/sales ordersEssentials, Go and Momentum plansCompare forecast and actual costs on a job or sales order to see a running profit. Forecast costs are copied from the quotation or entered when an item is added. Actual costs come from linked POs, manual entry, stock allocation, or the forecast. Report on them in Report Center, Report Studio.