Supply and fix
A contracting arrangement in which the contractor both supplies all required materials and carries out the installation, taking responsibility for material costs, sourcing and quality under a single combined price.
In short
Supply and fix means one contractor buys the materials and installs them for a single price, carrying the risk on cost and quality. Itemize materials, labor, access and making good, and state exclusions before the quote goes out.
Supply and fix is a contracting arrangement in which one contractor buys all the required materials and installs them for a single combined price. It shows up as a quote line or heading (for example "supply and fix 40 m of ductwork"), as the scope of a subcontract order, and on the job as a materials cost and a labour cost that must both be tracked against the same price. The contractor owns the sourcing, the material cost and the quality of what goes in, as well as the installation. Supply and fit means the same thing and is the common phrase in domestic and shopfitting work. It is widely used across the construction and trade sector.
How supply and fix works in practice
The contractor measures the work (a quantity take-off), prices materials at current supplier rates, adds a waste allowance, prices labour, and adds overhead and profit. The customer sees one price, or a price per item, and pays that regardless of what the materials cost the contractor. Any rise in material prices after the quote, any quantity shortfall and any extra waste comes out of the contractor's margin unless the quote says otherwise.
The other common arrangement is labour-only, where the customer or main contractor supplies the materials and the subcontractor supplies the workforce. Many businesses run both, so each job needs to be recorded under the right contract type or material costs end up against the wrong job.
Worked example
A fit-out contractor quotes to supply and fix a run of partition and ceiling work:
- Materials at current supplier prices: £4,200
- Waste allowance of 5%: £210
- Labour, 12 operative days at £240: £2,880
- Access equipment hire: £350
- Making good: £280
- Cost subtotal: £7,920
- Overhead and profit at 15% of cost: £1,188
- Quoted price: £9,108
If the supplier raises material prices by 10% between quote and order, materials cost £420 more. The price stays at £9,108, so the contractor's overhead and profit allowance falls from £1,188 to £768. A written price confirmation from the supplier, or a short validity period on the quote, prevents this.
Where supply and fix goes wrong
The usual failures are vague scope and missed costs. A one-line "supply and fix" price with no itemization invites disputes about what was included. Access equipment, delivery, waste removal and making good are the lines most often left out. Customers also assume that "supply" means the exact product they had in mind, so name the make, model or specification, or state "or equivalent".
Itemize and state exclusions
Break the price into materials, labour, access and making good, name the products, and list what is excluded. Even when a customer only sees one total, an internal breakdown shows you where margin was lost.
Warranties are the other trap. Because the contractor supplied the product, the customer will look to the contractor for defects in both the product and the installation, so check what your supplier's warranty covers before you quote.
Quoting supply and fix
Build the quote from live supplier costs and keep materials and labour as separate lines internally. Tools such as quotes in Zigaflow can hold cost and sell price per line, so margin is visible before the quote leaves. For related terms, see the glossary.