Smart Export Guarantee: how solar installers help customers get paid

Beginner10 min read

Zigaflow Editorial

Published

Zigaflow Editorial publishes Zigaflow's guides, insights, industry resources, glossary and workflow pages. Zigaflow is responsible for what they say. Spotted an error? Email support@zigaflow.com.

In short

The Smart Export Guarantee pays customers for exported solar power, but their application depends on documents the installer issues. Send the MCS certificate, network operator notification and export meter details together as one handover pack.

  • The SEG is paid by the customer's chosen licensed supplier, but the installer supplies the evidence the application needs.
  • Issue the MCS certificate, network operator notification and export meter details together as one handover pack.
  • Put the certificate number, notification reference and meter serial on a single cover sheet that matches the documents.
  • Check the export meter position at survey, because a customer without a suitable meter cannot be paid.
  • Never quote expected earnings, since each licensee sets its own rates and terms.

A customer's Smart Export Guarantee application succeeds or stalls on paperwork the installer controls. Here is how to issue the MCS certificate, network operator notification and export meter details as one handover pack, so customers get paid sooner and call you less.

The Smart Export Guarantee (SEG) is a Great Britain scheme, launched on 1 January 2020, under which electricity suppliers that have opted in as SEG licensees pay small-scale generators for low-carbon electricity they export to the grid. The supplier pays the customer, not the installer and not the government. Before a customer can claim, the installer has to supply three things: the MCS certificate proving the installer and products were certified, evidence the installation was notified to the network operator, and the export meter details the supplier needs to measure and pay for exports.

Most of the support calls an installer receives about the SEG come from one source: the customer is ready to apply and one of those three documents is missing, late or buried in an email. This guide sets out how to issue them as a single handover pack so the application goes through the first time.

Why the application stalls on the installer's paperwork

Ofgem is clear that a customer applies directly to a SEG licensee, and that the licensee sets the rate, contract length and terms. The tariff must always be above zero, and payments are calculated from export meter readings. The customer can choose any licensee, not just their current supplier. None of that is in your hands.

What is in your hands is the evidence. MCS says a customer is eligible if the system was installed by an MCS certified installer using certified products, and that a supplier might ask for the MCS certificate when the customer signs up. It also says the customer needs a smart meter that records exported electricity. One third-party guide goes further and lists network operator notification under G98 or G99 as a third condition, so it is sensible to treat that confirmation as part of the pack too, even though suppliers differ in what they ask for.

The pattern is simple. A customer who cannot find the certificate number, or does not know what an export meter reference is, cannot finish the supplier's form. They ring you. A handover pack that already contains the answers removes the call.

Scope

The SEG applies to installations located in Great Britain. Eligible technologies include solar PV up to 5MW, so a domestic system is well within the limit. Northern Ireland sits outside the scheme.

What goes in the SEG handover pack

Think of the pack as one document, or one folder, with a cover sheet that answers the questions a supplier's application form asks. Include these items.

The MCS certificate. The certificate itself, plus the certificate number and the date of issue written clearly on the cover sheet. The customer will be asked for it, and a number they can copy is better than a PDF attachment they have to open.

The network operator notification. The reference and date for the G98 notification or G99 application, with the name of the network operator. If you have already filed it, see our guide to filing a DNO notification after a solar install.

The export meter details. Whether the property has a smart meter or an export meter that can measure at half-hourly intervals, and the meter's serial number. Ofgem's guidance and the MCS page both tie payment to export meter readings, so a customer without a suitable meter will not be paid, however good the paperwork is. Where the customer needs to request a smart meter from their supplier, say so on the cover sheet.

System facts. Installation address, system capacity in kW, technology type and commissioning date. These are the details suppliers typically ask for, and they should match the certificate exactly.

A plain-language next step. Three lines telling the customer to choose a licensee, compare tariffs, and apply using the pack. Do not recommend a tariff. Rates and terms vary by licensee and change, and the choice is the customer's.

Issuing the pack in practice

1

Confirm the export meter position at survey

Ask whether the property has a smart meter or export-capable meter during the site survey, not at handover. If the customer needs a new meter, they can start that request while you install, so it is not the last thing holding up payment.

2

Notify the network operator before or at commissioning

File the G98 notification or G99 application for the installation, and record the reference and the date on the job record. A missing notification is the gap most likely to surface later.

3

Issue the MCS certificate and record the number

Once the commissioning data is complete, issue the certificate through your MCS process and copy the certificate number onto the job record.

4

Collect the meter details

Record the meter serial number and note whether it records exports at half-hourly intervals. If the supplier has not yet fitted a suitable meter, mark the pack as pending on this line.

5

Build the cover sheet

Put the certificate number, network operator reference, meter details, system capacity and commissioning date on a single page that matches the supporting documents exactly.

6

Send everything in one message

Send the cover sheet, certificate and notification confirmation together, in one email or one portal link, so nothing is lost across separate threads.

7

Check back after a set period

Contact the customer a couple of weeks after handover to ask whether they have applied. If they are stuck, you can see which document they are missing.

Where Zigaflow fits in

None of this needs special software. A checklist and a shared folder work. But the pack is easier to keep consistent when the data lives in one place. In Zigaflow, document templates let you produce the cover sheet from the same job data every time, so the certificate number and capacity on the cover sheet cannot drift from the job record. The jobs record holds the notification reference and meter details alongside the quote and the invoice, and project tracking lets you see which installations have reached handover without a complete pack. For the wider picture on running solar work, see renewables and solar.

Do not promise income

Never state what a customer will earn from exports. Rates are set by each licensee, vary widely and change, and some tariffs carry conditions. Tell the customer what documents they have, not what they will be paid.

Common gaps and how to close them

A few failures repeat. The certificate number is typed incorrectly on the cover sheet, so check it against the certificate. The notification is filed but the reference was never recorded, so add it as a required field before a job can be closed. The customer is told to apply but does not know the licensee does not have to be their current supplier, so say it in the pack, as Ofgem does. For eligibility questions on the customer's side, our guide to checking SEG eligibility and applying is written for them and you can point them to it.

Finally, treat the pack as part of the sale. A customer who gets paid soon after installation is more likely to recommend you, and one who spends weeks chasing paperwork tells people about that instead.

Common questions

The customer's chosen SEG licensee pays it. A SEG licensee is an electricity supplier that offers a SEG tariff, and it does not have to be the customer's current energy supplier. Ofgem says each licensee sets the rate, contract length and other terms, although the tariff must always be above zero and payments are calculated from export meter readings. The installer is not involved in payment, only in supplying evidence.