How long DNO approval takes and what delays it
In short
DNO approval is the longest fixed block of time on a renewables or EV charging programme, and delays almost always come from poor application documents rather than network capacity. Submit the application when the survey is booked, with accurate documents, and track it as a dependency.
- A G99 application is required for any generation above 3.68 kW per phase and must be submitted before commissioning, not after the equipment order.
- Even a fast-track G99 application carries a minimum 10-working-day window before commissioning is permitted, and the process can run to three months.
- The DNO application belongs on the programme from the point of survey booking, with installation dates made conditional on determination rather than ahead of it.
- Most DNO application delays are caused by incomplete or inaccurate technical documents, not network capacity constraints.
- Confirmation of commissioning must be filed with the DNO within 28 days of energising the system, closing the G99 process as a compliance requirement.
DNO approval - the formal permission from your Distribution Network Operator before a generating or exporting installation connects to the grid - is the longest fixed-duration item on any renewables or EV charging programme. This guide explains when you need it, how long it takes, and why almost every delay comes down to document quality rather than network capacity.
DNO approval is the formal permission process managed by a Distribution Network Operator - the company that owns and operates the local electricity network serving a property - before a generating or exporting installation can connect to that network. You need formal approval rather than a simple notification when the system you are installing generates or exports more than 3.68 kW per phase: that threshold is the boundary between EREC G98 and the G99 application. For commercial solar, battery storage systems, and larger electric vehicle charging installations that export to the grid, G99 approval is almost always required. Under the EREC G99 standard, even a fast-track application carries a minimum 10-working-day window before commissioning is permitted, and the standard allows the process to run to three months for the same category. Full applications requiring detailed technical assessment take longer still. That span is the single largest fixed block of time on any renewables or EV charging programme, and the installers who account for it early finish on time. The ones who submit after the order is signed are the ones calling customers to explain a delay.
Why the application belongs before the survey, not after the order
Most programmes run in this sequence: survey, quote, customer accepts, equipment ordered, then apply to the DNO. At that point the application is filed with equipment on order, an installation crew provisionally booked, and a customer expecting a live system within weeks. The DNO then takes the time it needs.
This sequencing mistake is the most common source of programme overrun in the renewables sector. The DNO review period does not shorten because equipment has arrived or because a customer is waiting. Moving the application earlier - ideally submitted at the same time the survey is booked - means approval lands before the installation date is locked rather than after it.
The usual argument for waiting until after the order is: "we need the exact equipment specification to complete the form." This is partly true, but the information the DNO actually needs to begin its assessment - system capacity, export limit, protection settings, and a site single-line diagram - is all available at the design stage. The specific inverter model can be confirmed before the DNO reaches a decision. The information that cannot change without restarting the application is the site address, the connection point, and the generation capacity. Those are known before the survey is even booked.
What the DNO actually reviews
Understanding what the distribution network operator assesses explains why document quality drives outcomes more than network capacity does. The DNO's job is to confirm that connecting your installation will not destabilise the local network. A well-prepared application gives the engineer everything needed in one pass. A poorly prepared one gets queried, returned for clarification, and goes back to the assessment queue.
The documents that most commonly cause delays when incomplete or inaccurate are the single-line diagram, the protection settings declaration, the export limit specification, and the site MPAN details. Each of these is within the installer's control to get right before submission.
The six steps to managing DNO approval without delaying the programme
Confirm which connection route applies to your installation
Check the generation capacity against the 3.68 kW-per-phase threshold that separates G98 notification from G99 approval. Any system above that threshold, including the majority of commercial solar, battery storage exporting to the grid, and large EV charging hubs with export capability, requires a G99 application before commissioning. For electric vehicle charge point installations where the new maximum demand of the property including the charger exceeds 60A per phase, a prior application is also required. Applications for these larger installations are submitted through the ENA Connect Direct platform or directly to the local DNO; confirmation from the DNO is required before the charger goes live.
Prepare your technical documentation at the design stage - before submitting
Gather the four documents the DNO needs before you open the application form. The single-line diagram must show the actual connection topology for this site: how the generation equipment connects to the meter point, where any protection relays sit, and how the export limiting scheme operates. A template diagram that has not been updated for the site will be returned. The export limit must be clearly specified with the control mechanism described, not simply stated as "limited." Site MPAN details must match the DNO's records exactly.
Submit the G99 application at the point of survey booking
Submit the application as early as the design allows - the goal is to have it in with the DNO while the programme is still in its early stages. For fast-track G99 applications (single installations, type-tested inverters, capacity within the applicable thresholds, loss-of-mains protection confirmed), use Form A1-2 as published by the ENA. For installations outside the fast-track criteria - higher capacity systems, complex protection arrangements, or sites where network reinforcement may be needed - use the standard application route and allow proportionally more time. Send the application to the correct channel for your local DNO: some require submission via ENA Connect Direct, others have their own portals or accept email submissions.
Application route selection
Before submitting, check all fast-track conditions in EREC G99. It is faster to identify the correct route before submission than to resubmit after a return.
Set a commissioning date that respects the minimum approval window
When completing the application, the planned commissioning date must be at least 10 working days from the date you submit - and within three months of that date. The ENA confirms this requirement for fast-track G99 applications. If your installation date is within 10 working days of when you plan to submit, adjust either the submission date or the installation date before filing. For full G99 applications, allow more buffer, since the technical assessment takes longer.
Monitor the application and respond to any DNO queries within five working days
After submission, treat the application as an active correspondence rather than a document posted and forgotten. DNOs issue queries by email and expect a response within their stated period. An unanswered query pauses the determination and may cause the application to be returned. Assign a named person in your business who is responsible for checking the application email address and responding to queries on every active job. Log the submission date, the expected determination date, and any query-and-response events against the project record. If the DNO's determination is approaching the maximum window and you have not received a decision, contact the DNO's connections team directly.
Energising before approval
If the installation date has moved ahead of the DNO decision, delay energisation rather than commissioning early and attempting to regularise later.
Confirm commissioning to the DNO within 28 days of energising the system
Once the system is energised, EREC G99 requires confirmation of commissioning to be submitted to the DNO within 28 days. For fast-track applications, this confirmation is made on Form A3-2 as published by the ENA. Where commissioning tests are not witnessed by the DNO, the confirmation must still be submitted within this window. Create a reminder in your project management system at the point of commissioning so that the 28-day deadline is tracked as a task, not left to memory.
Placing DNO approval on the programme
The programme entry for the DNO application should have two dates visible to whoever is managing the job: submission and expected determination. Both should link to downstream programme tasks.
Submission should trigger from the same event that triggers the site survey booking, or in some businesses, earlier. Determination should be a dependency for two things: placing the equipment procurement order and booking the installation crew. If determination slips, the installation date moves. That dependency relationship needs to be explicit in the programme, not understood informally.
Managing multiple active jobs with open DNO applications is where tracking discipline pays the most. When a DNO application is submitted for one job, it should create a visible dependency flag on that job's installation date. A business running ten or twenty active projects needs to see the DNO status of each job in a single view, not buried in individual job files.
After commissioning, the 28-day confirmation window is a separate tracked task - not an afterthought. The system may be working perfectly and the customer happy, but the confirmation still needs to be filed within the 28-day window.
The DNO application is the part of a renewables or EV charging programme with the longest minimum duration, the most external dependencies, and the least tolerance for a late start. Submitted early, prepared accurately, and tracked as an active programme dependency rather than an admin task, it adds no delay to any project. Left until the order is placed, prepared in a hurry, and treated as a form to file and forget, it becomes the reason programmes miss their dates.
Sources
- Smart Export Guarantee (SEG)Ofgem · accessed 2026-09-11
- Connecting commercial generation to the electricity networksEnergy Networks Association · accessed 2026-09-11
- Connecting electric vehicles and heat pumps to the networksEnergy Networks Association · accessed 2026-09-11
- Frequently asked questions about connecting to the networksEnergy Networks Association · accessed 2026-09-11